Analysis Of The Earned Value Concept In Project Monitoring (Case Study: Construction Work For The Development Of Faculty Of Forestry Building, University Of North Sumatra Phase 1)

by ADMIN 180 views

Introduction

Construction projects often face a high level of complexity, requiring careful management to achieve the desired goals. In the construction project of the Faculty of Forestry Building, University of North Sumatra Phase 1, there are common challenges, such as late progress and cost swelling. Therefore, monitoring becomes a crucial step in project control, which allows identification of cost deviations and schedules in a timely manner. To increase the effectiveness of the monitoring of this project, the earned value concept method (earned value concept) is used as the main approach.

Background of the Study

The earned value concept is a project management technique used to measure project performance by comparing the actual cost of work performed (ACWP) with the budgeted cost of work performed (BCWP) and the budgeted cost of work scheduled (BCWS). This concept is widely used in various industries, including construction, to ensure that projects are completed on time, within budget, and to the required quality standards. The earned value concept provides a comprehensive view of project performance, enabling project managers to identify areas of improvement and make informed decisions to mitigate risks and ensure project success.

Methodology

This research begins with data collection from the project site. The data obtained were then analyzed by paying attention to three main indicators: Actual Cost of Work Performed (ACWP), Budgeted Cost of Work Performed (BCWP), and Budgeted Cost of Work Scheduled (BCWS). After the analysis is carried out, the final result of all data is presented to provide a clear picture of the current project conditions.

Data Analysis

The results of the analysis conducted until the 20th week showed that the BCWS value was Rp 14,816,705,720, BCWP of Rp 4,614,975,520, and ACWP reached Rp 4,153,562,199. From these data, we can calculate the value of the Cost Performance Index (CPI) and the Schedule Performance Index (SPI). The CPI value obtained is 1,111, which shows that the project spends a smaller actual fee compared to the value of the work that has been completed. Meanwhile, the SPI value recorded at 0.311 indicates a significant delay in the project schedule.

Results and Discussion

From these two indicators, we can draw the conclusion that even though the project has saved costs, delay in completion of work is the main problem that must be overcome. The final estimate of the project costs (EAC) is calculated at Rp 20,301,199,616, while the estimated time for the completion of the project (ECD) is estimated to be 52 weeks.

Conclusion

The importance of applying the concept of the value of the results in the construction project cannot be ignored. This method not only helps in monitoring progress and costs, but also provides a basis for better decision making to minimize the risk of unexpected delays and expenses in the future. Thus, comprehensive and accurate analysis of project data is very important in ensuring the success of the construction project, including in the construction of the Faculty of Forestry Building, University of North Sumatra.

Recommendations

Through the use of the concept of the value of the results, it is expected that project management can be more responsive in overcoming the issues that arise and make adjustments to the strategy in a timely manner to ensure that the project can be completed according to the specified budget and time. Therefore, it is recommended that project managers use the earned value concept as a tool to monitor project performance and make informed decisions to ensure project success.

Limitations of the Study

This study has several limitations. Firstly, the data used in this study is limited to the 20th week of the project, which may not be representative of the entire project duration. Secondly, the analysis of the data is based on a single project, which may not be generalizable to other projects. Therefore, further research is needed to validate the findings of this study and to explore the application of the earned value concept in other projects.

Future Research Directions

Future research can build on the findings of this study by exploring the application of the earned value concept in other projects, including those in different industries and with different project characteristics. Additionally, research can be conducted to investigate the effectiveness of the earned value concept in improving project performance and reducing project risks.

Conclusion

In conclusion, this study demonstrates the importance of using the earned value concept in monitoring project performance. The results of this study show that the earned value concept can provide a comprehensive view of project performance, enabling project managers to identify areas of improvement and make informed decisions to mitigate risks and ensure project success. Therefore, it is recommended that project managers use the earned value concept as a tool to monitor project performance and make informed decisions to ensure project success.

Q: What is the Earned Value Concept?

A: The Earned Value Concept is a project management technique used to measure project performance by comparing the actual cost of work performed (ACWP) with the budgeted cost of work performed (BCWP) and the budgeted cost of work scheduled (BCWS).

Q: What are the three main indicators used in the Earned Value Concept?

A: The three main indicators used in the Earned Value Concept are:

  1. Actual Cost of Work Performed (ACWP): The actual cost incurred to complete the work.
  2. Budgeted Cost of Work Performed (BCWP): The budgeted cost of work completed.
  3. Budgeted Cost of Work Scheduled (BCWS): The budgeted cost of work scheduled to be completed.

Q: What is the Cost Performance Index (CPI)?

A: The Cost Performance Index (CPI) is a measure of project performance that compares the actual cost of work performed (ACWP) with the budgeted cost of work performed (BCWP). A CPI value of 1 indicates that the project is performing as planned, while a value greater than 1 indicates that the project is under budget.

Q: What is the Schedule Performance Index (SPI)?

A: The Schedule Performance Index (SPI) is a measure of project performance that compares the budgeted cost of work scheduled (BCWS) with the actual cost of work performed (ACWP). An SPI value of 1 indicates that the project is performing as planned, while a value greater than 1 indicates that the project is ahead of schedule.

Q: What are the benefits of using the Earned Value Concept?

A: The benefits of using the Earned Value Concept include:

  1. Improved project performance: The Earned Value Concept provides a comprehensive view of project performance, enabling project managers to identify areas of improvement and make informed decisions to mitigate risks and ensure project success.
  2. Better decision making: The Earned Value Concept provides a basis for better decision making, enabling project managers to make informed decisions about project resources, timelines, and budgets.
  3. Reduced project risks: The Earned Value Concept helps to identify potential project risks and enables project managers to take proactive steps to mitigate them.

Q: How can the Earned Value Concept be applied in different industries?

A: The Earned Value Concept can be applied in various industries, including construction, IT, manufacturing, and more. The key is to adapt the concept to the specific needs and requirements of each industry.

Q: What are the limitations of the Earned Value Concept?

A: The limitations of the Earned Value Concept include:

  1. Data quality: The accuracy of the Earned Value Concept depends on the quality of the data used to calculate the indicators.
  2. Complexity: The Earned Value Concept can be complex to implement and interpret, requiring specialized knowledge and skills.
  3. Limited scope: The Earned Value Concept is primarily focused on cost and schedule performance, and may not capture other important aspects of project performance.

Q: How can the Earned Value Concept be integrated with other project management tools and techniques?

A: The Earned Value Concept can be integrated with other project management tools and techniques, such as:

  1. Project management software: The Earned Value Concept can be integrated with project management software to provide a comprehensive view of project performance.
  2. Risk management: The Earned Value Concept can be used to identify and mitigate project risks.
  3. Quality management: The Earned Value Concept can be used to ensure that project deliverables meet the required quality standards.

Q: What are the future directions for the Earned Value Concept?

A: The future directions for the Earned Value Concept include:

  1. Development of new indicators: New indicators can be developed to provide a more comprehensive view of project performance.
  2. Integration with other project management tools: The Earned Value Concept can be integrated with other project management tools and techniques to provide a more comprehensive view of project performance.
  3. Application in different industries: The Earned Value Concept can be applied in various industries, including construction, IT, manufacturing, and more.